Katana VentraIP

Kori Nuclear Power Plant

The Kori Nuclear Power Plant (Korean: 고리원자력발전소, Hanja: 古里原子力發電所) is a South Korean nuclear power plant located in Kori, a suburban village in Busan. It is the world's second largest fully operational nuclear generating station by total reactor count and the number of currently operational reactors since 2016, after it exceeded in nameplate capacity Canada's Bruce Nuclear Generating Station. It is owned and operated by Korea Hydro & Nuclear Power, a subsidiary of KEPCO. The first reactor began commercial operation in 1978 and operated until 2017 when it was decommissioned. Units 2, 3, and 4 started commercial operations in the 1980s. All reactors on site are pressurized water reactors.

Kori Nuclear Power Plant

고리원자력발전소 (kori)

Operational

Unit 1: 1 August 1972
Unit 2: 23 December 1977
Unit 3: 1 October 1979
Unit 4: 1 April 1980
Unit 5: 16 June 2006
Unit 6: 5 June 2007
Unit 7: 16 October 2008
Unit 8: 19 August 2009

Unit 1: 29 April 1978
Unit 2: 25 July 1983
Unit 3: 30 September 1985
Unit 4: 29 April 1986
Unit 5: 28 February 2011
Unit 6: 20 July 2012
Unit 7: 20 December 2016
Unit 8: 29 August 2019

Unit 1: 18 June 2017

PWR

1 × 1882 MWth
2 × 2912 MWth
2 × 2825 MWth
2 × 3983 MWth

7489 MW (net)

74.45%
(includes Units 1 & 7)

43,148 GW·h (2016)
(includes Units 1 & 7)

Incidents[edit]

Minor incidents[edit]

On 9 February 2012, during a refueling outage, loss of off-site power (LOOP) occurred and emergency diesel generator (EDG) 'B' failed to start while EDG 'A' was out of service for scheduled maintenance, resulting in a station blackout (SBO). Off-site power was restored 12 minutes after the SBO condition began.


The LOOP was caused by a human error during a protective relay test of the main generator. The EDG 'B' failing to start was caused by the failure of the EDG air start system. Further investigation revealed that the utility did not exercise proper control of electrical distribution configuration to ensure the availability of the Station Auxiliary Transformer (SAT) while conducting test on the Unit Auxiliary Transformer (UAT).


After restoring off-site power through the SAT, the operators eventually recovered shutdown cooling by restoring power to a residual heat removal pump. During the loss of shutdown cooling for 19 minutes, the reactor coolant maximum temperature in the hot leg increased from 37°C to 58.3°C (approximately 21.3°C rise), and the spent fuel pool temperature slightly increased from 21°C to 21.5°C. There was no adverse effect on the plant safety as a result of this event, no radiation exposure to the workers, and no release of radioactive materials to the environment. However, inconsistent with the requirements, the licensee did not report the SBO event to the regulatory body in a timely manner and did not declare the "alert" status of the event in accordance with the plant emergency plan. The licensee reported this event to the regulatory body about a month after the event had occurred.[11]


On 2 October 2012 at 8:10 a.m., Shin Kori-1 was shut down after a warning signal indicated a malfunction in the control rod system which triggered an investigation to verify the exact cause of the problem.[12]


In June 2013, Kori-2 was shutdown, and Kori-1 ordered to remain offline, until safety-related control cabling with forged safety certificates is replaced.[13] Control cabling installed in the APR-1400s under construction failed flame and other tests, so need to be replaced delaying construction by up to a year.[14]


In October 2013, cable installed in Shin Kori-3 failed safety tests, including flame tests. Replacement with U.S. manufactured cable delayed the startup of the plant,[14][15] which eventually entered commercial operation 3 years late.[5]

Nuclear power in South Korea

List of commercial nuclear reactors in South Korea

Media related to Kori Nuclear Power Plant at Wikimedia Commons

Kori plant overview